Order tasks so every prerequisite comes before the task that depends on it. This works on directed acyclic graphs (DAGs).
Prerequisites: Basic C++ input/output, vectors, loops, and the preceding graph lessons.
Build the idea
- Count each vertex’s incoming edges.
- Put every zero-indegree vertex into a queue.
- Remove a vertex, append it to the order, and decrement its neighbors’ indegrees.
- If fewer than n vertices were removed, the graph contains a directed cycle.
- in[v] counts remaining prerequisites. A cycle leaves vertices with positive indegree, so the processed count is smaller than n.
C++17 implementation
This is a complete program. Compile with C++17 and enter the input described below.
// Key idea: in[v] counts remaining prerequisites. A cycle leaves vertices with positive indegree, so
// the processed count is smaller than n.
#include<iostream>
#include<vector>
#include<queue>
#include<deque>
#include<stack>
#include<algorithm>
#include<functional>
#include<numeric>
#include<utility>
using namespace std;
vector<int>topo(const vector<vector<int>>&g){
int n=(int)g.size()-1;
vector<int>in(n+1),order;
for(int v=1;v<=n;++v){
for(int u:g[v]){
++in[u];
}
}
queue<int>q;
for(int v=1;v<=n;++v){
if(!in[v]){
q.push(v);
}
}
while(!q.empty()){
int v=q.front();
q.pop();
order.push_back(v);
for(int u:g[v]){
if(--in[u]==0){
q.push(u);
}
}
}
if((int)order.size()!=n){
return {};
}
return order;
}
template<class T>void printValues(const vector<T>&values){
for(int i=0;i<(int)values.size();i++){
if(i>0){
cout<<' ';
}
cout<<values[i];
}
cout<<'\n';
}
int main(){
ios::sync_with_stdio(false);
cin.tie(nullptr);
int n,m;
cin>>n>>m;
vector<vector<int>>graph(n+1);
for(int i=0;i<m;i++){
int a,b;
cin>>a>>b;
graph[a].push_back(b);
}
vector<int>order=topo(graph);
if(order.empty()){
cout<<"CYCLE\n";
}
else{
printValues(order);
}
}
Complexity analysis
O(V + E) time, O(V) auxiliary space.
Example input and output
Read n m and m directed edges a b, meaning a must precede b (n≥1). Print a topological order, or CYCLE. Several valid orders may exist.
Input
4 3 1 2 1 3 3 4
Output
1 2 3 4
Only vertex 1 initially has indegree zero. Removing it makes 2 and 3 available, and processing 3 releases 4.
Practical applications
Use topological order for prerequisite scheduling and dynamic programming on DAGs.
Check your understanding
When does a topological order exist?
Put it into practice
Output a valid order for courses with prerequisites, or report a cycle.
Show a hint
Represent prerequisite → dependent course.